There is a mountain of literature
about increasing the parallelism of projects to improve performance. While many
have found this approach beneficial, others have seen it create havoc in their
projects. It is important to have some insight into the dynamics of dependencies
to understand how increased degree of overlap in activities can have
such a high potential for both positive and negative consequences on a project.
"Accelerate the work available"
The first intended consequence of increased degree of overlap
in activities is to increase the amount of work available at once. Assuming
resources are available this can greatly accelerate the speed at which a project
is done. In our modeling work on projects, we have found that a increase in
the overlap of work in the early stages of the project can make a substantial
difference in the overall time for the project. Preston Smith in his book Creating
Products in Half the Time calls this early phase the "fuzzy front end"
and he indicates that most organizations have substantial opportunities to increase
cycle time by improving in this area. This loop is self-reinforcing. As you
raise the degree of overlap in activities, the number of activities
available for work goes up, and assuming that resources are available, the
number of activities completed also goes up which make even more work
available. It has been clearly demonstrated in the literature and several case
studies that most assumptions about what is possible in terms of overlap is
far too conservative. People tend to blend what is possible with what they perceive
to be affordable. Is building the second story of a house dependent on the first
floor being complete or even started? Not if there is a crane available. In
this case, it may be possible, but necessarily not smart financially. In some
cases time may be so valuable, that creative ideas about breaking apparent dependencies
may be welcome even at extremely high cost.
"Resolve Interface Issues
Early"
The second intended consequence of increased degree of overlap
in activities is the reduction in work caused by concurrent engineering.
If done properly, the increase in overlap will help force communication on
interface issues to be dealt with early. This decreases the rework between
functions and phases. Less rework means less unplanned activities
and more resources allocated to the planned activities of the project.
This helps to accelerate the project creating more time and earlier surfacing
of interface issues. This is a self-reinforcing loop that rewards the team that
increases overlap by eliminating non-value-added rework.
"Build on Poor Dependencies"
The unintended consequence of the increased overlap of activities
is the increase in the error rate caused by starting work before the dependencies
are completely set. Dependencies will change at times. If much of the work is
done in parallel, the dependent activities will have to be reworked or scrapped
when changes are made. This increase in work tends to pull time away from concurrent
engineering activities and can set up a vicious cycle where error generation
can create even more errors in future work.